Transmission Line Energization Study

Transmission Line Energization Study

In this article, Transmission Line Energization Study is demonstrated using Power Systems Computer Aided Design (PSCAD) software.

This study illustrates the key points considered in a line energizing study. The PSCAD ‘Multiple-Run’ component is used to time the instant at which the three poles of the circuit breakers are closed.

This study considers energizing the line when it is fully de-energized. However, the worst case is more likely when the line is energized (re-energized), when there is ‘trapped charge’ on the line. The re-energization of the line is not covered in this article.

System Overview

Below figure shows a typical high voltage ac network consisting of 400 kV and 115 kV transmission lines:

High Voltage Network Modelling in PSCAD
High Voltage Network Modelling in PSCAD

The 210 km single circuit line (400 kV) between Station A and Station B is the focus of the line energizing study. The line is energized from Station A. The circuit breaker at Station B is open.

Thus, E2 is the open end voltage of the energized line as per below figure:

The 210 km Line between Station A and Station B
The 210 km Line between Station A and Station B

Important Features of Network Modelling

Important features of the network model are as follows:

  • The network details up to two buses away from Station A.
  • The rest of the system is represented by Thevenin’s equivalence voltage sources.
  • Detailed ‘frequency dependent’ line models for transmission lines.
  • The model includes surge arresters at Station A as well as the line end surge arrester at Station B

Network Equivalence

The parameters of the voltage source(s) representing the ‘remote’ buses must accurately represent the fault current contribution from the ‘remote’ system. As well, the voltage magnitude and the phase angle must correspond to the specific system operating condition (i.e. load flow condition).

As such, we proceed as follows:

  • We enter the positive and zero sequence impedance of the ‘remote’ system calculated based on the fault levels.
  • We enter the voltage source magnitude and phase angle corresponding to the system operating condition.
  • Note that prior to performing the energizing study, the correct steady-state power flow in different parts of the network should be verified (i.e. conduct a comparison with known power flow conditions).

Transmission Line Data

Below figure and table shows the typical data corresponding to a 400 kV line used in this example simulation:

Conductor Height and Spacing
Conductor Height and Spacing
Conductor Data
Conductor Data

Surge Arrester Data

Below table shows the surge arrester characteristics used in this example. The rated voltage of the surge arresters (connected from line to ground) in this example is 335 kV. This is typical for a 400 kV system. The PU voltage (as per below table) is based on the surge arrester rated voltage. Slope of the V-I Characteristic curve must reduce as current increase.

Surge Arrester Data
Surge Arrester Data

Objectives of Line Energizing Study

The main objectives of a line energizing study are to demonstrate the following:

  • The peak switching overvoltage is less than the ratings of the substation switching surge insulation levels.
  • The energy dissipation in the surge arrester during the switching surge is within the surge arrester energy rating.

Simulation Results

In this study, the multiple-run component of PSCAD is used to energize the line at different points on the voltage waveform. All three breaker poles close at the same instant. Thus, this example does not cover the pre-strike phenomenon of an individual breaker pole.

The multiple-run unit is set up to repeat the simulation 106 times. On each run, the breaker B1 closes at a different point on the voltage waveform.

The simulation results shown in below figure are for the worst case, in which the line end voltage (E2) attains its largest peak value (approximately 600 kV or 1.85 PU).

Worst Case Simulation Results
Worst Case Simulation Results

Note that the surge arrester energy dissipation is around 70 kJ. These values must be compared with relevant equipment ratings.

Note that the transients at Station A bus are less severe than at the remote end of the line.

Below table shows the statistical summary of the line energizing results (i.e. multiple runs):

Statistical Summary of Line Energizing Study
Statistical Summary of Line Energizing Study

The description of the values displayed in above table are as follows:

  • Minimum and Maximum: These are minimum and maximum values observed in the study sample (i.e. peak overvoltage – raw data).
  • Mean and Std. Dev.: These are the mean value and the standard deviation of the data sample.
  • 2% level: Statistically, 2% of line switching events will results in peak over- voltage levels less than this value.
  • 98% level: Statistically, 98% of line switching events will results in peak over- voltage levels less than this value.

Hints

The following are some helpful hints for during the study:

  • Use the ‘Snapshot’ feature to speed up the multiple-run simulations.
  • Disable graphic animations during multiple runs to speed up the simulation.

Relevant Contents

Related Posts

Transformer Inrush
PSCAD
Ashish

Transformer Energization Studies

Transformer energization studies are performed to demonstrate that the resonant overvoltages are well damped and that the magnitudes do not violate temporary overvoltage capability of station equipment. During transformer energization, two main phenomena occur: an inrush current and a voltage

Read More »
Capacitor Bank Switching
PSCAD
Chief Editor

Switching of Capacitive Circuit

Introduction Shunt capacitors, connected between line and neutral or line and ground, are common sights on power systems. They may be there to correct a lagging power factor or in cases, to provide voltage support for the system. The transient

Read More »
Switching an Inductive circuit
Power System Analysis
Ashish

Switching Of An Inductive Circuit

Introduction Switching of an inductive circuit deserves special attention because this operation may lead to high-voltage transients. These transients can damage the involved equipment. Inductive loads are those components capable of generating a magnetic field and typically consist of solenoids,

Read More »
switching transient
General
Ashish

Introduction to Power System Switching Transients

Introduction Power system switching transients occur each time, an abrupt circuit change occurs. This circuit change is usually the result of a normal switching operation, such as breaker opening or closing or simply turning a light switch on or off.

Read More »

Author Information

Comments

2 Responses

Leave a Reply

Your email address will not be published. Required fields are marked *